Techno Legal Cell
Settlement of Disputes through
Arbitration
Clause 25 of the Standard Forms PWD 7 & 8 and other relevant
clauses in other forms provides for appointment of an Arbitrator, in case of
disputes arising out of the contract at any stage between the parties to the
contract. It is the term of this Clause
that the arbitration shall be conducted in accordance with the provision of
Arbitration & Conciliation Act 1996 (26 of 1996). The provision of Arbitration Clause 25 can be
invoked by the contractor as well as by the Engineer- in- Charge. On receipt of request of the claimant for
appointment of an Arbitrator, the Chief Engineer or Head of the Department, in
the absence of a Chief Engineer, appoints an Arbitrator within 30 days from the
receipt of such request as contained in Section 11 of Arbitration Act
1996. If the CE fails to appoint an
Arbitrator within 30 days, then the appointment can be made, upon the request
of the party, by the Chief Justice or his designate.
Request for Appointment
The contractor gives a list of all disputes to the CE. Except the
action taken under Clause 2 for levy of compensation for delay in execution of
work and other clauses where exceptions have been provided, all the disputes
are referred to the Arbitrator. The
contractor cannot have re-course to Court of Law for redressal of his grievances unless he has exhausted the
channel of arbitration. Such request for
appointment of Arbitrator is to be made within 120 days of the intimation to
the contractor about preparation of final bill or within 30 days of rejection
of his claims by the CE.
Appointment and Award with Reasons
The Government of
The authority of the appointed Arbitrator does not become revocable except with the order of the Court. The sole
Arbitrator shall adjudicate the matter within 4 months . However this period is extendable with the
consent of both the parties.
The Arbitrator writes the award on stamp papers (Non Judicial) and
record reasons where total amount of disputes exceeds Rs.
1.0 lac and publishes the award. After publication of award it is examined
whether it is acceptable to the Govt. or not.
Upon examination of the award, if the Department is of the opinion that
the award should be challenged, the advice of Ministry of Law is obtained and
action is taken on the basis of their advice generally.
Limitation Time for Appeal
The application for correction of award under Section 33 is required
to be made within a period of one month from the receipt of award. The application for setting aside the award
is to be made within 3 months. Further,
if however, the court is satisfied it can condone the delay of 30 days but not
thereafter. Under Act of 1940, the award
was only enforceable by the leave of the court and after making a decree. But in the Act of 1996, the Arbitrator’s award is
deemed to be a decree of Court after a period of 3 months has elapsed and no
application can be made for challenging the arbitration award.
Techno Legal Cell headed by Superintending Engineer, attached with the
CE (CSQ), handles all Arbitration cases and related matters, where the claim
amount exceeds Rs. 10 lakh. The SE (TLC) at HQ looks after the cases of
The powers for acceptance or challenging arbitration award to officers
are given below:
CE - Award amount i/c interest -
7 Lakh
ADG - -do- - 20 Lakh
DG(W) - -do- - Full powers
Section 36 of CPWD Manual Vol. II deals this matter in detail. A very
large number of cases are being handled by the officers of this department
which consumes the precious working time and other resources.