MAJOR PROJECTS BEING HANDLED by CPWD (31st Jan 2009)

 

1           Works for Sports Authority of India

a.      Commonwealth Games-2010

·        Upgradation of existing infrastructure for the five major stadia of the Sports Authority of India at New Delhi . These are as under:

        1.      Jawahar Lal Nehru Stadium

2.      Indira Gandhi Indoor stadium

3.      Dr. Karni Singh Shooting Range

4.      Major Dhyan Chand National Stadium

5.      SPM Swimming Pool Complex

Apart from above

 

        o The detailed planning for all the venues is almost complete and the project has already entered into execution stage. Work is in progress at Jawahar Lal Nehru Stadium; Indira Gandhi Indoor stadium; Major Dhyan Chand National Stadium and SPM Swimming Pool.   
All related jobs have been planned for completion latest by December 2009 leaving adequate time for trial runs before commissioning. The EFC has approved a rough cost limit of Rs. 1100/- crores   A dedicated project team has been formed for all these time bound works.

b.     Major programmes/ schemes implemented

·        Development of standardized the contracts/specifications etc. for modern hockey fields and synthetic athletic tracks

·        Laying of synthetic tracks for athletics and hockey at many locations

2     Development of Roads in Bihar

·        Rashtrya Sam Vikas Yojna:

o       2000 Km. of State highways in 33 districts of Bihar costing Rs. 3000 cr

o    CPWD has been entrusted Development of State Highways in Bihar in 33 districts for length of about 1705 km. The project costing about 2400 crores is to be completed by 2010 – 11. For execution of this project, one zone has been created at Patna by diverting the existing strength of CPWD. The work has been divided in 30 road packages & 25 bridge packages. The work in 27 road packages covering the length about 1577 km costing about 2000 crores & 21 bridge packages costing about 171 crores for 106 bridges has already been started. The work in 2 road packages for about 90 km length costing about 110 crores was awarded but agencies failed to start the works & their Earnest Money & Performance Guarantee was forfeited but the Hon’ble High Court, Patna granted a stay which has been finally vacated & re-invited tenders are under acceptance. This has delayed these works for about a year. Tenders for 4 bridge packages for 12 Nos of bridges costing about 71 crores are likely to be awarded by March ’09. Implementation of one Road package covering around 38 km had been kept in abeyance by Govt. of Bihar. The entire project is likely to be completed by the year 2010-11. The expenditure upto Dec.’08 shall be 860 crores, with about 35% financial progress, which is likely to go upto 1200 crores by March ’09 with about 50% physical progress. The expenditure during financial year 2009-10 is likely to be around 900 crores with about 90% financial progress upto Dec.’08, about 80% earthwork in widening, 60% road widening, 35% Bituminous work & 50% cement concrete road shall be completed.

Existing Road Final Road

 

·        Pradhan Mantri Gramin Sadak Yojna

o       1222 Km. of Roads in 4 districts in Bihar costing Rs.600 Cr.

o  CPWD is constructing Rural Roads under Pradhan Mantri Gram Sadak Yojana in Bihar in districts of Begusarai, Darbhanga, Madhubani and Samastipur. A Circle dedicated to PMGSY works under a Project Manager opened in June-2005. Connectivity being provided to unconnected villages having population of 1000 and more under Bharat Nirman Yojana by construction of link roads and associated through routes.

The work is challenging in the sense they are being located in remote areas where access is very difficult. A number of places are flood affected and remains cut off during rains. Adequate Cross drainage work in the form of pipe culverts, slab culverts, minor bridges and a few major bridges are also being provided. Many of the area has law and order problem as antisocial elements like Naxalites and other criminals are very active. The contractors are few and reluctant to tender for fear of anti-social element.

As per the specification of rural road, PMGSY roads are being constructed with carriageway width of 3.75m and Roadway width of 7.5m. The road crust consists of two layers of WBM (Gr. II & Gr III)  layers each 75mm thick over granular subbase whose thickness is based on CBR of subgrade and traffic condition and generally 200mm thick. 20mm thick premix carpeting layer has been provided as wearing course. In the inhabitated areas or wherever there are chances of submergence of road during floods, cement concrete roads 190mm thick with M30 grade of concrete over 150mm thick granular subbase layer have been provided.

 

Particulars

Length

(KM)

Const. Cost

(Rs. in Lakh)

Maint. Cost

(Rs. in Lakh)

Total

(Rs. in Lakh)

i.

Total Length of road approved by MORD

1969

99547

8495

108042

ii.

Work awarded

837

39888

3246

43134

 

(a)

Work completed

239

6061

630

6691

 

(b)

Works in progress

598

33827

2616

36443

iii.

Tenders Received

130

7750

681

8431

iv.

Tenders invited

721

38372

3553

41925

v.

DPRs sent for Revision to NRRDA

606

36889

3336

40225

vi.

Release of fund Expenditure

(Rs. in Lakh)

 

Financial Year

Release

Expenditure

2005-06

86.34

86.34

2006-07

3705.32

2865.49

2007-08

8568.00

6246.91

2008-09

5346.57

6533.83

Grand Total

17706.23

15732.57

 

3    Construction of General Pool Accomodation

·        Residential:

o       350 Quarters have been added during 2007-08.

o       45 quarters have been added up to December 2008.

·        Non-residential :

o       5790 sqm of accommodation completed during 2007-08.

o       Office Accomodation at Delhi, Hyderabad and  Port Blair (In Progress)

4        Border Roads, Fencing & Flood Lighting Works

§         Construction of Border Roads, Fencing & Flood Lighting Works along Indo-Pak Border, Indo-Bangladesh Border and approach roads to Indo-China Border in Sikkim and Uttaranchal.

§         Maintenance of the infrastructure created along the Indo-Bangladesh Border in the form of 2558 Km roads, bridges, flood lighting etc.

5       Works for Inland Waterways Authority of India

·        Facilitate development of the Inland waterways for transportation of goods and people in India similar to that of National Highways but at a much more economical rate.

·        Planning and designing & execution of ‘jetties’ at Guwahati and Patna . 

6           Construction of permanent houses for tsunami affected people of A&N Islands

·        Out of 9797 houses to be built for the Tsunami affected people in the Islands 7966 are being built by CPWD.

·        2704 houses have been completed up to December 2008.

7        Works in Kabul, Afghanistan on behalf of the Ministry of External Affairs, Govt of India. These include:

o       Repair and rehabilitation have been completed for

§         Habibia School

§         Indira Gandhi Institute for Child Health.

o       Planning  for Indian Chancery Building (in progress) 

o       New Afghan Parliament (in progress).

8        Office Building for Ministry of External Affairs at New Delhi - Jawahar Lal Nehru Bhawan

9        Kendriya  Vidyalayas at various locations in the country.

10  Tsunami Reconstruction Plan of Andaman and Nicobar Island

11   Execution of works related to the Health sector by CPWD

            ·   Currently CPWD is also involved in planning, designing and up-gradation of 4 hospitals at Jammu, Srinagar, Varanasi and Dhanbad under Pradhan Mantri Swasthya Suraksha Yojna. The work of up-gradation of I.M.S., BHU, Varanasi was entrusted to CPWD by M.H. & F.W. vide No. Z-29013/1/2004-SSH dated 21.9.2006 for comprehensive planning, designing and execution.   M/s Hospitech Management Consultants Pvt.Ltd., Consultant was appointed for comprehensive planning and designing consultancy.  The D.P.R-1 for Rs. 72.95 crores was submitted before P.M.C. on 20.2.2008 which was accepted with the direction to invite the tenders.  Work has been awarded to M/s Era Infra Engg. Ltd.., New Delhi with tendered amount of Rs.52.15 crores.estimated date of completion is 06.06.2010.
 About 50% Hospital area shall be air-conditioned with latest energy effective screw chilling plant as per ECBC norms.  Un-interrupted power supply in emergency shall be meet out with UPS - 2X100 KVA and D.G. sets 2000 KVA with standby arrangement.  The building shall also equipped with voice communication centre with EAPBX for 1000 lines and LAN and IBMS with C.C.T.V.  All mandatory provisions like fire fighting, re-cycling of waste have also to be provided. The Hospital shall provide facilities for General Surgery, Neurosurgery, Cardiothoracic surgery, Orthopedics and its allied Super Specialties with composite care hook up. The completion of work shall be made in 20 months.

                                                       Upgradation of Institute of Medical Sciences, BHU, Varanasi