MAJOR PROJECTS BEING HANDLED by CPWD
1
Works
for Sports Authority of
a.
Commonwealth
Games-2010
·
Upgradation
of existing infrastructure for the five major stadia of the Sports Authority of
India at
1.
Jawahar
Lal Nehru Stadium
2.
Indira
Gandhi Indoor stadium
3.
Dr.
Karni Singh Shooting Range
4.
Major
Dhyan Chand National Stadium
5.
SPM
Swimming Pool Complex
Project
completed and handedover
b.
Major
programmes/ schemes implemented
·
Development
of standardized the contracts/specifications etc. for modern hockey fields and
synthetic athletic tracks
·
Laying
of synthetic tracks for athletics and hockey at many locations
2
Development
of Roads in
·
Rashtrya
Sam Vikas Yojna:
A Tripartite MoU was signed on 27-04-2005 among CPWD, Govt. of Bihar & MoRTH, Govt. of India for Development of State Highways under Rastriya Sam Vikas Yojana (RSVY). The total scope of work given to CPWD for strengthening and widening of Roads was for 2044.63 km but restricted to 1715.280 km. The project with the revised cost of Rs. 2727.89 Cr. is to be completed by 2012-13. The entire work was been divided in 34 Road packages, 25 Bridge packages and 3 Road Signage packages. The expenditure from 2006 - 07 to end of the year 2011-12 is Rs. 2315.94 Cr. with 95% physical progress. The progress of the works due to delay in forest clearance, land acquisition problem for approach roads of newly constructed bridges, non shifting of utilities by BSEB, Govt. of Bihar and delay in approval of Revised Estimate by Planning Commission, Govt. of India etc. Out of the Road length of 1690 km. completed, 1043.71 km has so far been handed over to RCD, Govt. of Bihar. The remaining Road length of 24.65 km. is likely to be completed by June 2012 and the entire road length is targeted to be handed over to RCD by Dec 2012. Out of 114 bridges, 85 bridges have been completed and opened to traffic with balance 29 bridges likely to be completed by March 2013 including construction of approaches of bridges for which work is being taken up.
·
Pradhan
Mantri Gramin Sadak Yojna
·
1841
Km of Rural Roads in 4 districts in
·
CPWD
is constructing Rural Roads under Pradhan Mantri Gram Sadak Yojana in
· The work is challenging in the sense that these are located in remote areas where access is very difficult. A number of places are flood affected and remains cut off during rains. Adequate Cross drainage work in the form of pipe culverts, slab culverts, minor bridges and a few major bridges are being provided. Many of the area has law and order problem as antisocial elements like Naxalites and other criminals are very active. The contractors are few and unprofessional and had been reluctant to tender for fear of anti-social element.
· The contract is drawn on the basis of Standard Bidding Document (SBD) as approved by NRRDA which is based on the World Bank pattern. Note worthy feature of SBD is that each contract has a defect liability and maintenance period of 5 Years after construction. It is a fixed cost contract and no cost escalation or cost compensation clause exists.
· As per the specification of rural road, PMGSY roads are being constructed with carriageway width of 3.75m and Roadway width of 7.5m. The road crust consists of two layers of WBM (Gr. II & Gr III) layers each 75mm thick over granular subbase thickness of which is about 200 mm based on CBR of subgrade and traffic conditionsk. 20mm thick premix carpeting layer has been provided as wearing course. In the inhabitated areas or wherever there are chances of waterlogging due to inadequate drainage, cement concrete roads 190mm thick with M30 grade of concrete over 150mm thick granular subbase layer have been provided.
· Detailed Status of work as on April 2012 is as below:-
Particulars
|
Length
(KM)
|
Const.
Cost
(Rs.
in Lakh)
|
Maint.
Cost
(Rs.
in Lakh)
|
Total
(Rs.
in Lakh)
|
||
i.
|
Total Length of
road approved by MORD
|
1841 |
101065 |
8588 |
109653 |
|
ii.
|
Work awarded
|
1841 |
99632 |
8520
|
108152 |
|
|
(a)
|
Work
completed
|
1224 |
59257 |
5087 |
64344 |
|
(b)
|
Works
in progress
|
617 |
40375 |
3433
|
43808
|
· Most of the running works are in advance stage of progress and targeted to be completed by December 2012.
![]() |
![]() |
![]() |
![]() |
3
Construction
of General Pool Accommodation
·
General
Pool Office Accommodation At CBD, Shahdara,Delhi
The General Pool Office Complex at Sub-Central Business District Shahdra, Delhi on a plot measuring 1.9 Acres has been constructed by the CPWD. CPWD architect planned the building as GPOA with double basement for parking. Building is having two front blocks G+4 and rear blocks as G+6 with two tier basement. The total plinth area of the building is 17343 sqm including basement area of 6607 sqm. Sanction of Rs. 43.14 Cr. was received from MOUD on 01.04.2008. Entire project was divided into 8 broad packages for the execution purpose. The work physically started in the month of July 2008 and completed in Oct 2011. ....more
![]() |
![]() |
![]() |
![]() |
·
Residential:
·
350
Quarters have been added during 2007-08.
·
45
quarters have been added up to December 2008.
·
Non-residential
:
·
5790
sqm of accommodation completed during 2007-08.
·
Office
Accomodation at
4
Border
Roads, Fencing & Flood Lighting Works
·
Construction
of Border Roads, Fencing & Flood Lighting Works along Indo-Pak Border,
Indo-Bangladesh Border and approach roads to Indo-China Border in Sikkim and
Uttaranchal.
·
Maintenance
of the infrastructure created along the Indo-Bangladesh Border in the form of
2558 Km roads, bridges, flood lighting etc.
5
Works
for Inland Waterways Authority of
·
Facilitate
development of the Inland waterways for transportation of goods and people in
·
Planning
and designing & execution of ‘jetties’ at Guwahati and
6
Construction
of permanent houses for tsunami affected people of
·
Out
of 9797 houses to be built for the Tsunami affected people in the
·
2704
houses have been completed up to December 2008.
![]() |
![]() |
8
· Jawaharlal Nehru Bhawan, the headquarters office building of the Ministry of External Affairs at Janpath,New Delhi,is a contemporary state-of-the-art building in complete harmony with its environment and surrounding architecture of Edwin lutyen’s.
· Jawaharlal Nehru Bhawan is the first ECBC compliant Govt. Building which will have Green Building Certification with ‘LEEDS’. The plot of land measuring 7.785 Acres (31,504 sqm.) is situated on the crossing of Maulana Azad road and Janpath. The total built up area of the building is 59,475 sqm including basement area of 28,075 sqm to accommodate parking and services such as electric sub-station, pump room, DG set etc. The total cost of the project is apprx. Rs. 232 Cr. ....more
![]() |
![]() |
![]() |
![]() |
![]() |
9
Kendriya
Vidyalayas at various locations in the country.
11 Execution of works related to the Health sector by CPWD
·
Currently CPWD is also involved in planning,
designing and up-gradation of 4 hospitals at
Upgradation of Institute of Medical Sciences, BHU, Varanasi